FeasaFeasa Feasability

Address withheld, Everett, WA

Parcel withheld · City of Everett, Snohomish County · Prepared Nov 2026 · sample report

81 · GO

GO

Completing the already permitted 748 square foot backyard home is the right path: the city has already reviewed and issued a building permit, a site work permit, and a water and sewer utility permit for it, and nothing in the zoning, critical area, or civic record found in this study unsettles that approval. What decides it now is keeping those permits active with a timely inspection and closing a small number of confirmation gaps, such as the unit's exact distance to each lot line, that only the non public site plan can finally settle.

What holds it back most

  • Recorded covenants or plat notes on the late-1950s plat that could bar a second dwelling Could end itLikely fine+5 if it clears
  • Legal lot of record Could end itRemote+2 if it clears
  • Site work and stormwater scope under the site work permit, declared at $350,000 and not in the budgetToss-up+5 if it clears

See everything it takes to reach a GO ▾Hide ▴

What moves the meterIf a document settles itIf you check its step
Recorded covenants or plat notes on the late-1950s plat that could bar a second dwelling Could end itLikely fineIf it goes wrong: ends the planSettle it: Order a title report.+5No score change
Legal lot of record Could end itRemoteIf it goes wrong: ends the plan+2No score change
Site work and stormwater scope under the site work permit, declared at $350,000 and not in the budgetToss-upIf it goes wrong: a large unbudgeted site and drainage costSettle it: Request the approved site plan and building plans from the city's permit file.+5No score change
Fire hose-pull distance to a rear unit on a lot about 170 feet deepToss-upIf it goes wrong: an unbudgeted sprinkler system or access conditionSettle it: Ask the fire marshal's office whether the backyard home's distance from the street meets the fire department's access or hose-pull limit.+3No score change
Side sewer alteration: shared 4 inch lateral where a shared line must be 6 inchesToss-upIf it goes wrong: a new or upsized side sewer not pricedSettle it: Ask the city's permit office what scope of work the side sewer alteration under permit [utility permit withheld] covers.+3No score change
Not checked: electric service and separate metering for the backyard homeToss-upIf it goes wrong: an unpriced service run, meter or panel upgrade+3No score change
Permits lapse if no inspection by May 5, 2027Likely fineIf it goes wrong: reapplication with new fees and months of delaySettle it: Schedule the first required inspection before the permits lapse.+1No score change
Recorded easements through the backyard building areaLikely fineIf it goes wrong: a shifted or reshaped footprintSettle it: Order a title report.+1No score change
City seismic and liquefaction layers not queriedLikely fineIf it goes wrong: a geotechnical report and foundation changesSettle it: Ask the city's planning office whether its seismic hazard and liquefaction susceptibility layers flag this parcel.+1No score change
Main house's 1960 permit history not foundLikely fineIf it goes wrong: after-the-fact permit paperworkSettle it: Ask the city's building division for the 1960 house's original permit record.+1No score change
Possible change to the water and sewer connection fee scheduleLikely fineIf it goes wrong: a small fee correctionSettle it: Ask the city's permit office whether the water and sewer connection and system development fee schedule changed effective September 2026.+1No score change
As-built setbacks and lot coverage not independently confirmedRemoteIf it goes wrong: a small siting correctionSettle it: Request the approved site plan and building plans from the city's permit file.+0No score change

It is a GO.

Aerial view of the property
Figure 1. The parcel as photographed in the Snohomish County 2024 orthophoto. It does not show the backyard home itself, since that imagery predates the permits this study reviewed.
Critical areas
Figure 2. Every wetland, flood, landslide, erosion, and stream layer this study checked, drawn over the same 2024 orthophoto, with none reaching this parcel. It does not show the one advisory geology layer that touches the lot, since that layer is background soil context, not a hazard.
Utilities
Figure 3. The water and sewer mains the city maps near the frontage, drawn over the same 2024 orthophoto. It does not show the new three quarter inch water service or the side sewer alteration approved under permit [utility permit withheld], since neither is yet reflected in the city's utility map.

The parcel

FindingStatusSource
Parcel number and county[parcel withheld], Snohomish County, inside the City of Everettverified
Lot sizeabout 13,000 square feet by the county assessor's record, 0.29 acres; about 13,000 square feet by the GIS parcel outline, a 0.4 percent difference within normal mapping toleranceverified
Legal descriptionthe recorded plat, lot withheld, recorded in the late 1950sverified
The existing houseBuilt 1960, one story, about 1,400 square feet, wood frame construction with lap siding, assessed in good condition. The county assessor's own record lists three bedrooms and one full bathroom; a third-party aggregator site this study also checked lists five, and the assessor's own figure is preferred hereverified for size, year, and condition; inferred for bedroom count
The house's own permit historyNot found in the records this study could reach; the city's open online permit table does not go back to 1960, and its older paper file is not searchable without a records requestunknown (open question 2)
The backyard homeA 748 square foot, single story detached accessory dwelling unit, called the accessory unit, approved October 14, 2026 and issued November 6, 2026 under building permit [building permit withheld], with a matching site work permit [site work permit withheld] and a water and side sewer utility permit [utility permit withheld] issued the same dayinferred, confirmed twice against the city's own open permit table, which carries no reviewer sign off beyond the data itself
Ownership[owners withheld], who have held the parcel continuously since September 2003 and are the owners of record on the new permits; the last recorded transfer was a self to self conveyance, not an arm's length saleverified
Recorded easementsNone found crossing the parcel or the backyard where the new unit sits, in the county's general easement layer or its drainage easement layerinferred, a title report is the only way to see every recorded easement
Covenants or plat restrictionsNot found in the records this study could reach; the county's recorded documents search now requires a registered accountunknown (open question 5)
Sewer and waterConnected to the City of Everett's public water and sewer system since 1980; no septic system is on file for this parcelinferred from the utility and septic record GIS layers, not a records-office certification
Flood zoneNot in a mapped Special Flood Hazard Areaverified

Zoning

This parcel is zoned NR, Neighborhood Residential, under the City of Everett's current zoning code. The city's own zoning map layer returns this zone but carries no listed edit date, so this study cross checked it against the zoning table adopted by Ordinance 4102-25, effective July 8, 2025; the two agree, so NR is the current, confirmed zone (Everett Municipal Code 19.06.010, Table 6-1).

A single detached dwelling and an accessory dwelling unit behind it are both allowed outright in the NR zone. Everett's use table treats every kind of home, including an accessory unit, as one consolidated "dwelling unit" use (Everett Municipal Code 19.05.080, Table 5-1), and the NR zone carries no cap on the number of dwelling units a lot may hold; Everett removed its density caps citywide in 2025 (Everett Municipal Code 19.06.100).

An accessory dwelling unit in the NR zone, attached or detached, is allowed up to two per lot and is capped at just under 1,000 square feet of interior living area (Everett Municipal Code 19.04.030; 19.06.110(C)). The approved backyard home is 748 square feet, comfortably under that cap, so it qualifies for every accessory unit allowance the code gives. Washington's own statewide floor for accessory dwellings, RCW 36.70A.681, sets the same two unit minimum, bars an owner occupancy requirement, and guarantees a roof no lower than 24 feet unless the main house's own limit is lower. That floor applies here in full, because the one state exception, for a lot carrying a mapped critical area or its buffer (RCW 36.70A.681(4)), is not triggered on this parcel, as the Critical areas section below confirms.

Height: a detached accessory unit in NR follows the same table as the main house, three floors or 35 feet (Everett Municipal Code 19.22.020, Table 22-1, as the city's own permit services guidance applies it to accessory units). The approved unit is a single story, so it sits well under that limit.

Setbacks: an accessory dwelling unit's setbacks are the same as a principal building's in the same zone (Everett Municipal Code 19.06.020(F)): 10 feet at the front, 5 feet at the rear where there is no alley, and 5 feet on each side (Table 6-2). This study could not independently confirm the exact distance from the built unit to each lot line, because the approved site plan is not a public document; the city's own plan reviewers already checked this before issuing the permit, so this is a confirmation gap rather than a known problem (see Open questions, row 16).

Lot coverage: the NR zone allows up to 50 percent of the lot covered by buildings, rising to 55 percent once a second dwelling unit is on the lot (Everett Municipal Code 19.06.010, Table 6-1, footnote 2). Even taking the house and the new unit together at their full floor areas, about 1,400 plus 748 equals 2,194 square feet against the about 13,000 square foot lot, which comes to about 17 percent, far under that limit.

Parking: no off street parking is required for a dwelling unit under 1,200 square feet anywhere in Everett (Everett Municipal Code 19.34.050(C)); the 748 square foot unit qualifies.

Owner occupancy: Everett repealed its owner occupancy requirement when it rewrote its accessory dwelling rules in 2025; none applies here (repeal of Everett Municipal Code 19.08.100 by Ordinance 4102-25; RCW 36.70A.681(1)(b)).

The existing house, built in 1960 under whatever setback and coverage rules applied at the time, has not been found to violate today's rules, and there is reason to think it would not: Everett's front setback in NR dropped from 20 feet to 10 feet in the 2025 rewrite, so today's standard is looser than the one the house was likely built to meet, not stricter. This study found no code enforcement record, violation, or demolition flag against the house, which is a further, though not conclusive, sign that it carries no legal problem for a new accessory unit sited behind it. The house's own original 1960 permit record could not be reached through the sources checked here; nothing found points to a problem, but nothing confirms the house's own permit history that far back either (see Open questions, row 2).

Pending changes: Everett's City Council adopted a land division ordinance, Planning Commission Resolution 26-04, on October 14, 2026, implementing the state's new lot split law. It rewrites subdivision procedure only, lowering the minimum lot size for a short plat in some zones and changing notice and appeal rules; it does not touch accessory dwelling or setback rules and has no effect on this project.

Critical areas

No critical area or hazard reaches this parcel on any layer this study checked, county or city: no wetland, whether from Snohomish County's own wetland layer, the National Wetlands Inventory, or the City of Everett's wetland layer; no stream or watercourse; no mapped landslide hazard, whether from the Washington Department of Natural Resources or the city's own landslide layer; no erosion hazard; and no Special Flood Hazard Area, on either the county's FEMA layer or the city's FEMA derived flood layer. The lot is also flat: a sample of 28 points across the parcel found a maximum slope of 0.6 percent and only 0.4 feet of elevation change from one side to the other.

The single hit anywhere near this parcel is the county's background geology layer, which shows the lot sitting on glacial till, an ordinary Puget Sound soil type. The county's own documentation is explicit that this is advisory geologic context, not a hazard designation, and it does not trigger Everett's 200 foot geotechnical report rule (Everett Municipal Code 19.37.230), which only applies within 200 feet of an actual mapped hazard.

Two things remain unconfirmed rather than clear. The City of Everett maps a separate seismic hazard layer and a liquefaction susceptibility layer that this study's pull did not query (see Open questions, row 4). And a new round of housekeeping amendments to Everett's critical area chapter was heard by the Planning Commission on October 20, 2026, but is not yet confirmed adopted; city staff describe it as about 50 non substantive corrections, not a change to any buffer or trigger, so it would not be expected to change anything found here even once adopted.

Because no critical area or buffer reaches this parcel, the one circumstance that would pull this lot out of Washington's accessory dwelling floor, RCW 36.70A.681(4), does not apply, and the state floor described under Zoning applies to this parcel without exception.

Utilities

The City of Everett is both the water and the sewer provider for this parcel, and has been since 1980, when the existing house's own water service and sewer lateral were installed, tied into an 8 inch sewer main and a 6 inch water main at the frontage. No septic system has ever been on file for this parcel in the county's on site sewage records.

The backyard home's own utility permit, [utility permit withheld], is for a new three quarter inch water service and an alteration to the existing side sewer, approved and issued alongside the two building permits. The new water service is consistent with Everett's requirement that a detached accessory dwelling unit carry its own separate meter (Everett Municipal Code 14.16.430). The side sewer alteration is less clear: Everett allows a shared side sewer under common ownership only where the shared section is at least 6 inches in diameter, and the City's utility map shows the existing lateral serving the main house at 4 inches. The permit description does not say whether the alteration upsizes that lateral, adds a separate line, or something else; this study could not settle which from the public record (see Open questions, row 8).

Electric service in this part of Everett, outside the city's own water and sewer utility, is ordinarily provided by Snohomish County PUD; this study did not independently confirm the provider for this specific parcel (see Who to contact next).

No connection moratorium was found for the City of Everett's Direct Water Service Area or Direct Sewer Service Area, which this parcel sits inside, as of this study (see The civic record). Separately, this study found a possible update to the city's utility connection and system development fee schedule, discussed under Fees the city publishes, that could not be confirmed because the city's own fee page would not load for an automated check.

What fits

MeasureValue
Lot areaabout 13,000 square feet, assessor; about 13,000 square feet, GIS outline
Lot width by depth75.0 feet by 169.9 feet
Front setback10 feet
Rear setback, no alley5 feet
Side setbacks, each5 feet
Net area free of any setbackabout 9,900 square feet
Existing house floor areaabout 1,400 square feet
Approved backyard home floor area748 square feet
House and backyard home together, against the lotabout 17 percent

Areas from the county parcel map, the assessor's building record, and the approved permit; a survey can move them.

Across the roughly 9,900 square feet that sits free of every setback on this lot, the 748 square foot backyard home is a small fraction, more than twelve times smaller than the room available. The unit fits the lot by a wide margin under the setback math alone, which is consistent with the city's own plan review having already cleared it before the permit issued. The one thing this study cannot confirm on its own is the unit's exact distance to each lot line, because the site plan behind the permit is not a public record (see Open questions, row 16).

PathCan it be done?What decides it
Backyard home, the accessory unit, 748 square foot detached accessory dwelling unitYes, already approved and permittedKeeping the issued permits active through inspection before they lapse

The backyard home fits the lot by a wide margin, and the city has already confirmed as much by issuing the permit; what remains is finishing the work the permit allows, not re-testing whether it fits.

What stands in the way

FindingStatus
The exact as built setback distances and lot coverage for the accessory unit are not independently confirmed, because the site plan is not a public recordOpen, low risk since the city's own review already checked this
All three permits lapse if no inspection occurs by May 5, 2027Open, an ordinary construction timeline risk
Whether recorded covenants or plat notes on this recorded plat restrict a second dwellingOpen, no covenant or association found yet
The 1960 main house's own original permit record could not be found in the sources this study could reachOpen, no sign of a problem
Whether the City of Everett's seismic hazard and liquefaction susceptibility layers flag this parcelOpen, not yet queried
A possible change to the city's water and sewer connection fee schedule, effective date unconfirmedOpen, affects fee confirmation only
Whether the backyard home meets the fire department's apparatus access or hose-pull distance limit, given it sits toward the rear of a lot about 170 feet deepOpen, not yet checked
Whether the side sewer alteration under permit [utility permit withheld] upsizes the existing 4 inch lateral, since a shared side sewer needs at least 6 inchesOpen, scope unconfirmed

What it takes

  1. Schedule the first required inspection before the permits lapse. A building inspector handles this; book it through the city's permit portal once work is ready for a footing, framing, or other first inspection, since each completed inspection resets the lapse clock and the permits otherwise expire May 5, 2027.
    Cost
    no fee beyond what the permits already paid
    Time
    same day to a few weeks, depending on inspector availability
    Tells us: whether the project is actively moving toward completion or at risk of losing its permits.
  2. Request the approved site plan and building plans from the city's permit file. A public records officer handles this; it shows the backyard home's exact distance to each lot line and its share of the lot's building coverage.
    Cost
    $0 to $50
    Time
    1 to 4 weeks
    Tells us: whether the as built setbacks and lot coverage match the Neighborhood Residential limits exactly, closing the one confirmation gap this study could not settle on its own.
  3. Order a title report. A title company handles this; it lists every recorded covenant, plat note, and easement against the lot.
    Cost
    $250 to $600
    Time
    3 to 7 days
    Tells us: whether anything recorded against this recorded plat limits a second dwelling, and confirms there is no easement running through the backyard.
  4. Ask the city's building division for the 1960 house's original permit record. A public records officer handles this.
    Cost
    $0 to $50
    Time
    1 to 4 weeks
    Tells us: whether the main house itself carries a clean, permitted history, the precondition the already issued backyard home permit assumed.
  5. Ask the fire marshal's office whether the backyard home's distance from the street meets the fire department's access or hose-pull limit. A fire marshal handles this.
    Cost
    $0 to $50
    Time
    1 to 4 weeks
    Tells us: whether the permit already carries a sprinkler or access condition, or whether the unit's position behind a 1960 house on a deep lot raises a fire access question nobody has asked yet.
  6. Ask the city's permit office what scope of work the side sewer alteration under permit [utility permit withheld] covers. A permit technician handles this.
    Cost
    $0 to $50
    Time
    1 to 4 weeks
    Tells us: whether the alteration upsizes the existing 4 inch lateral to the 6 inches a shared line needs, or does something else.
  7. Ask the city's planning office whether its seismic hazard and liquefaction susceptibility layers flag this parcel. A planner handles this.
    Cost
    no cost, a public GIS query or a written request
    Time
    same day to 1 week
    Tells us: whether a geologic hazard this study's pull did not query reaches this lot, closing the last unchecked hazard layer.
  8. Ask the city's permit office whether the water and sewer connection and system development fee schedule changed effective September 2026. A permit technician handles this.
    Cost
    $0 to $50
    Time
    1 to 4 weeks
    Tells us: whether the fee figures in this study's numbers are still current or need a small correction.

Already on file

DateWhat it isRecord numberStatusWhat it means for youLinks
2026-11-11Snohomish County Assessor property account summary for parcel [parcel withheld]currentConfirms lot size, legal description, the main house's year built, size and condition, and ownership and sale history.Saved copy in your Documents, Source record
2026-11-06backyard home building permit [building permit withheld], issued 2026-11-06[building permit withheld]issuedHeld by the agency. Use the source record link and ask for this record number.Source record
2026-11-06Site work permit [site work permit withheld] for 748 sf backyard home, issued 2026-11-06[site work permit withheld]issuedHeld by the agency. Use the source record link and ask for this record number.Source record
2026-11-06Water/side-sewer utility permit [utility permit withheld], issued 2026-11-06[utility permit withheld]issuedHeld by the agency. Use the source record link and ask for this record number.Source record

Also checked

Studies and reports it needs

No study on Feasa's standard list applies to this parcel: there is no septic system to evaluate, no wetland to delineate, no in-water work, no prairie plant habitat, and no protected species survey this parcel's conditions would call for, since there is no critical area of any kind on or near the lot. The confirmation steps that remain for this project are administrative, listed in What it takes above, not a new environmental or engineering study. The one soil note on file, that the lot's glacial till substratum can limit infiltration, is a drainage design input for whoever engineered the site work permit's stormwater facility, not a study this report calls for on its own.

The numbers

Completing the already permitted backyard home, construction plus every fee the city's schedule sets for it, runs an estimated $185,223 to $395,797, centered around $296,120.

Backyard home, the accessory unit Recommended748 sf single-story backyard home, as stated in the issued building permit
ItemLowLikelyHigh
Construction748 sf at $220 / $367.50 / $500 per sf$164,560$274,890$374,000
Building permit and plan review fees$5,335$5,335$5,335
Impact feestransportation waived, school exempt, park fee halved for an ADU; bedroom count unconfirmed$567$1,134$1,701
Water and sewer connection and system development fees$14,761$14,761$14,761
Total$185,223$296,120$395,797

What this budget covers

Included:

Not included:

No floor plan was matched; construction is priced from published market costs per square foot.

Grading, drainage, and paving around the unit are covered by the separate site work permit [site work permit withheld], which carries its own declared job value of $350,000 on the city's record, more than twice the building permit's $148,708. This study could not independently break that figure down and so has not added it to the total above; it is worth confirming with Permit Services, since it is unusually high for site work alone and may include a value that belongs elsewhere on the application.

The fee lines above are built from the schedule in Fees the city publishes, below.

Fees the city publishes

FeeAmount
Building permit construction fee, bracket $100,000.01 to $500,000, applied to the permit's own $148,708 declared value$2,826.20
Building department plan review fee, 75 percent of the construction fee$2,119.65
Planning review of building plans, 10 percent of the construction fee$282.62
State Building Code Council fee$6.50
Electrical permit, new construction under 1,000 square feet$100.00
Transportation impact fee$0, waived for a net increase of one accessory dwelling unit
School impact fee$0, accessory dwelling units are exempt
Park impact fee$566.50 to $1,700.50, depending on bedroom count, reduced 50 percent for an accessory dwelling unit; bedroom count not confirmed in this study (open question 7)
Water non-refundable application fee$158.00
Water three quarter inch meter, complete service$4,234.00
System development fee, three quarter inch meter, water and sewer combined$9,433.00
Side sewer alteration fee$30.00
Stormwater system development fee, base rate$906.00

These figures come from the City of Everett's Residential Building Permit Fees schedule, its 2026 Impact Fee schedule, its Planning, Zoning and Land Use Fee Schedule, and its Utility and System Development Fees schedule, each effective January 1, 2026 unless noted, with fees due at permit issuance, which for these three permits was November 6, 2026. A possible update to the utility fee schedule's effective date, to September 2026, could not be confirmed because the schedule's own page would not load for an automated check (see Open questions, row 9, and What it takes, step 8).

The civic record

DateFindingSource documentStatus
2026-03-25Building permit [building permit withheld] applied forCity of Everett Open Data, Trakit Permitsverified
2026-06-09Site work permit [site work permit withheld] applied forCity of Everett Open Data, Trakit Permitsverified
2026-10-14Building permit [building permit withheld], site work permit [site work permit withheld], and water and sewer utility permit [utility permit withheld] all approvedCity of Everett Open Data, Trakit Permitsverified
2026-10-14City Council adopted Planning Commission Resolution 26-04, a land division ordinance unrelated to accessory dwellingsEverett approves reforms to land division process, HeraldNetinferred, from news coverage rather than the council's own minutes
2026-10-20Planning Commission heard a package of about 50 non substantive annual code corrections, including to the critical areas chapter; not yet confirmed adoptedPlanning Commission previews 2026 annual amendmentsinferred
2026-11-06All three permits issuedCity of Everett Open Data, Trakit Permitsverified
through 2026-11-11No code enforcement action, complaint, stop work order, or permit appeal found against this parcelCity of Everett open data catalog, which carries no such dataset, and a general web searchinferred

What was checked

BodyDocuments readCoversCould not reach
City of Everett Permit First Review By Tier (dataset c6k3-mamn)12026-11 (current snapshot only)Nothing
Everett City Council02026-08-25 to 2026-11-11not swept directly in Legistar/AgendaCenter; relied on news coverage (Herald Net) and search-indexed council agenda items for the Land Divisions ordinance and utility items instead of reading council minutes verbatim
Everett Planning Commission02026-08-25 to 2026-11-11status of PC Res. 26-04 confirmed via news coverage, not by reading Planning Commission minutes directly
City of Everett Open Data (Trakit permits, dataset 3w3u-656c)72009-01 to 2026-11 (all permit rows on parcel [parcel withheld])Nothing
Everett Hearing Examiner02026-08-25 to 2026-11-11appeal docket is not a public searchable database; no case for this parcel found by general web search, but the docket itself was not opened

What would change this verdict

  1. If the as built setback distances or lot coverage, once confirmed from the site plan, turned out not to match the Neighborhood Residential limits: see What it takes, step 2 (open question 16).
  2. If no inspection occurs before the permits lapse on May 5, 2027: see What it takes, step 1.
  3. If a title report turned up a covenant or plat note restricting a second dwelling on this recorded plat: see What it takes, step 3 (open question 5).

Open questions

The questionWhat it changesHow to settle itWho settles itCostTime
1. Where does the existing house sit on the lot, and does it meet setbacks?Decides room for a new unit and nonconforming status.Not published in a form Feasa can read yet. Site survey or the applicant's approved site plan would show the existing house's position and whether it meets setbacksowner or survey$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
2. Does the existing 1960 main house have a clean permit history (no open violations) that would support it as a legal, permitted structure a backyard home can be sited behind?Confirms the host structure's legality, a precondition for the already-issued backyard home permit [building permit withheld] and the ADU/backyard home ownership-occupancy rules that typically attach to the primary dwelling.Not published in a form Feasa can read yet. Public records request to the City of Everett Building Division, or a registered eTRAKiT 'Public' account search, for the 1960 original building permit and any subsequent permit history on the main houseCity of Everett Permit Services (PermitServices@everettwa.gov, 425-257-8810) or property-record agent$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
3. Does the backyard home meet the fire department's apparatus access or hose-pull distance limit, given it sits toward the rear of a lot about 170 feet deep?A unit beyond the fire code's access or hose-pull distance can require a fire sprinkler system or a dedicated fire access lane, adding real cost not priced in this study.Ask City of Everett Fire Marshal's Office in writing. Review the approved site plan and building plans (What it takes, step 2), and ask the Fire Marshal's Office whether the permit carries a sprinkler or fire-access condition.City of Everett Fire Marshal's Office$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
4. Does the City of Everett Seismic Hazard layer (GIS layer 22) or Liquefaction Susceptibility layer (layer 21, LIQUEFAC_1 field) flag this parcel?If moderate-to-high or high liquefaction susceptibility or a seismic hazard is mapped here, EMC 19.37.210(A)(2) designates it a geologic hazard area, triggering the same 200-ft geotech-assessment and setback regime already confirmed clear for landslide/erosion on this parcel.Not published in a form Feasa can read yet. Query City of Everett GIS MapServer layers 21 and 22 for parcel [parcel withheld], or ask Everett Planning for a parcel hazard summaryCity of Everett Planning & Community Development, (425) 257-8731no cost (public GIS query or a written request)same day to 1 week
5. Do recorded covenants, plat notes or association rules limit a second dwelling?Private restrictions can block a project the city would allow.Not published in a form Feasa can read yet. Order a title report or commitment, which lists all recorded CC&Rs, declarations and association documents against the lot by AFNtitle company (escrow/title order)$250 to $600 (Feasa estimate, get a quote to confirm)3 to 7 days (Feasa estimate, confirm when you book it)
6. Is the road in front of the lot public or private, and who maintains it?Decides access rights, frontage improvements and who must approve work.Not published in a form Feasa can read yet. Ask the road or utility agency named for this addressCity of Everett Public Works$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
7. How many bedrooms does the approved 748 sf backyard home (the accessory unit) have?Sets which tier of Everett's park impact fee applies; the fee is reduced 50 percent for an ADU but the dollar amount still depends on bedroom count.Ask City of Everett Permit Services, via a public records request in writing. Review the approved building plans in the city's permit file, which show the unit's bedroom count.City of Everett Permit Services, via a public records request$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
8. Does the side sewer alteration under permit [utility permit withheld] upsize the existing 4 inch lateral, since Everett only allows a shared side sewer under common ownership where the shared section is at least 6 inches?If the alteration upsizes the lateral or adds a new line rather than simply sharing the existing 4 inch pipe, there may be added cost beyond the permit's own fees.Ask City of Everett Permit Services in writing. Ask Everett Permit Services what scope of work permit [utility permit withheld] covers.City of Everett Permit Services$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
9. Has Everett's water/sewer connection and system-development-fee schedule (EMC 14.16.713 / 14.08.135) changed since the pack's 2026-01-01-effective figures were recorded on 2026-08-25?Would change the dollar amount of the already-paid water/sewer connection and SDC fees on permit [utility permit withheld], and the cost baseline for any future connection in the city.The City of Everett Permit Services (425-257-8810) system did not answer. Check again or ask them. Open the PDF in a browser (not an automated fetch) or call Permit Services to confirm whether EMC 14.16.713 / 14.08.135 water and sewer connection/SDC amounts changed effective 2026-09-01 from the pack's recorded $4,234 (3/4" water) and $9,433 (3/4" combined SDF) figures.City of Everett Permit Services (425-257-8810)$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
10. Which school district serves the lot?Decides which school impact fee applies.Not published in a form Feasa can read yet. Ask the road or utility agency named for this addressCity of Everett Planning Division, or Everett School District / Mukilteo School District directly$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
11. At what size does stormwater review apply to a new home or unit?Decides whether a drainage plan is needed.Not published in a form Feasa can read yet. Ask Everett Public Works/stormwater engineering for the EMC Ch. 14.28 new/replaced-impervious-surface threshold that triggers stormwater review for a residential ADU projectCity of Everett Public Works, (425) 257-8731$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
12. Which traffic impact fee area is the lot in?Sets the traffic impact fee.Not published in a form Feasa can read yet. Ask the road or utility agency named for this addressCity of Everett Permit Services / Traffic Engineering$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
13. What tree rules apply, and how many protected trees are on the lot?Can add permit steps and replacement cost.Not published in a form Feasa can read yet. Check EMC's tree/landscaping chapter and whether any protected trees are on the lot (not covered by this pack)Everett Planning, (425) 257-8731, or a live code read of EMC tree regulations$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
14. Has the Snohomish County Assessor updated the parcel's improvement value to reflect the new $148,708 backyard home yet?current vs. future property-tax assessed value and whether a near-term reassessment should be expectedAsk Snohomish County Assessor's Office in writing. Call or re-query the Snohomish County Assessor (425-388-3433) or retry the online property search for parcel [parcel withheld]; assessors typically do not reflect a new improvement in the roll until a field inspection/next valuation cycle, so given the permit issued only 5 days before this check (2026-11-06), the $158,200 improvement value on file almost certainly predates the backyard home.Snohomish County Assessor's Officenone (phone/online lookup)same day to a few weeks to confirm by phone; the roll update itself follows the county's next annual/field-inspection cycle
15. Which fire district serves the lot?Decides fire review, fire impact fee and access rules.Not published in a form Feasa can read yet. Ask the road or utility agency named for this addressCity of Everett Fire Department$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
16. Do the backyard home's as-built setback distances and resulting lot coverage match NR zoning limits?Identifies a residual confirmation gap -- the site/building plans behind the already-issued permit are not public, so the report cannot independently re-check the exact footprint against the 10'/5'/5'/5' NR setbacks and 55% two-unit lot-coverage cap. This is a confirmation gap, not a known violation, since the city's own plan review already checked it before approving and issuing the permit.Not published in a form Feasa can read yet. Review the approved site plan/building plans in the city's permit file (public records request or via the applicant) to confirm the backyard home footprint's distances to the NR setback lines (EMC 19.06.020 Table 6-2 and (F)) and resulting lot coverage against the 55% NR two-unit cap (EMC 19.06.010 Table 6-1 fn 2).owner via public records request to Everett Permit Services, or the applicant's plan set$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
17. Is there any pending capital-facilities or comprehensive-plan change specific to the the frontage street neighborhood (98208, south Everett/the local neighborhood area) that could affect utility capacity or future development?Would signal a future constraint or improvement to water/sewer capacity serving this specific area, distinct from citywide fee or procedure changes.Not published in a form Feasa can read yet. Check the City of Everett 2026 annual comprehensive plan docket (closed for 2026, reopens spring 2027) and the Capital Facilities Element directly, or ask Planning Division whether any CIP line item touches the the frontage street / the local neighborhood service area.City of Everett Planning Division (425-257-8731)$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
18. What class of street does the lot front (arterial, collector, local)?Sets the front setback and service-install cost.Not published in a form Feasa can read yet. Confirm WSDOT/city functional classification of the frontage street if ever needed for a non-setback purpose (e.g. access permit)City of Everett Public Works / WSDOT Local Public Roads$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)
19. How far is the nearest major transit stop?Can remove the parking requirement.Not published in a form Feasa can read yet. Check Everett Transit / Community Transit route maps for the nearest stop; note this is immaterial to the parking outcome here because EMC 19.34.050(C) already sets 0 required parking for any dwelling unit under 1,200 sf regardless of transit proximityEverett Transit / Community Transit trip planner$0 to $50 (Feasa estimate, get a quote to confirm)1 to 4 weeks (Feasa estimate, confirm when you book it)

Who to contact next

Start with Everett Permit Services, which already holds this project's file and schedules the inspection that keeps the permits active. No pre application meeting is required or useful at this point, since the permits are already issued; Everett's optional pre application meeting would cost $730 for a future project on this lot.

OfficeWhat to contact them aboutHow to reach themStatus
Everett Permit Services, also handling Public Works utility questionsScheduling the first inspection (What it takes, step 1); requesting the approved site plan and building plans (step 2); the 1960 house's original permit record (step 4); the side sewer alteration's scope (step 6); whether the utility fee schedule changed (step 8)(425) 257-8810 · PermitServices@everettwa.gov · https://onlinepermits.everettwa.govverified, August 25, 2026 (Everett's own site did not load when checked again; this entry is confirmed from the city's own published contact details as of that date)
Snohomish County Auditor, Recording divisionOrdering the title report (What it takes, step 3)(425) 388-3483 · recording@snoco.gov · https://www.snoco.org/RecordedDocumentsverified, November 11, 2026
Everett Planning DivisionWhether the city's seismic hazard and liquefaction susceptibility layers flag this parcel (What it takes, step 7)(425) 257-8731 · planning@everettwa.govverified, August 25, 2026 (Everett's own site did not load when checked again; this entry is confirmed from the city's own published contact details as of that date)
Snohomish County Health Department (on site sewage and drinking water program)Not needed for this project; the parcel is served by city water and sewer, not a well or a septic system425-339-5200 · SHD-Info@snoco.org · https://www.snohd.orgverified, November 11, 2026
Everett Fire Marshal's OfficeWhether the backyard home's distance from the street meets the fire department's access or hose-pull limit (What it takes, step 5)https://www.everettwa.gov/DocumentCenter/View/31184verified, August 25, 2026 (Everett's own site did not load when checked again; this entry is confirmed from the city's own published contact details as of that date)
Snohomish County PUD, electricElectric service to the backyard home, if not already arranged(425) 783-8272, option 3verified, August 25, 2026 (pack)
Snohomish County AssessorWhen the new backyard home's value will be added to the tax roll (open question 14)425-388-3433 · https://wa-snohomish.publicaccessnow.com/PropertyInformation/PropertySearch.aspxverified, November 11, 2026
Washington's one call utility locate serviceBefore any further digging on this lot, such as finishing the site work under permit [site work permit withheld]811verified

Sources

Septic, water & sewer

Permits, plans & recorded documents

Property, parcel & tax records

Environmental & shoreline records

Zoning & land use

Civic decisions & utilities planning

Contacts & agencies

Other sources

Costs