47 · CONDITIONAL GO
Up 3 since delivery
A 3 bed, 2 bath backyard home of 1,200 sf fits as a two-story on the open ground between the existing house and the frontage street, and state and city rules let it be sold as a condominium unit. It can be done once the city confirms how its landslide-prone mapping at the street end applies to a unit placed outside it, and how separate ownership fits the one-water-service rule and the city's power metering. The budget does not price the attorney's and surveyor's condominium work.
What holds it back most
See everything it takes to reach a GO ▾Hide ▴
| What moves the meter | If a document settles it | If you check its step |
|---|---|---|
| Landslide-prone mapping at the street end and whether its rules reach a unit just outside it Could end itLikely fineIf it goes wrong: The city applies its slide rules to the unit's spot and the engineer limits building there, leaving no other place to buSettle it: Ask the city whether the landslide-prone mapping touches a unit placed outside it. | +5 | No score change |
| Not checked: recorded covenants or plat notes that could bar a second home or condominium sale Could end itLikely fineIf it goes wrong: ends the plan or the condo sale | +5 | No score change |
| Condominium setup with the existing house as a unit: attorney, surveyor map and lender consent are not pricedLikely badIf it goes wrong: an unbudgeted legal and survey bill and months of delay before saleSettle it: Set up the condominium. | +8 | No score change |
| A 600 sf footprint fits outside the band only by about 1 ft (30 by 26 ft clear area, from an aerial estimate of the house)Toss-upIf it goes wrong: a smaller or taller unit, or building into the band with a geotech reportSettle it: Commission a boundary and topographic survey with tree locations. | +5 | No score change |
| Storm easement and agreement noted beside an 18-inch storm pipe near the left side lineToss-upIf it goes wrong: a narrower unit or a redesignSettle it: Get copies of the recorded storm easement and agreement. | +5 | No score change |
| Separate water and power meters for a condominium-owned unit under the one-service-per-parcel ruleToss-upIf it goes wrong: shared services under a recorded agreement, a weaker condo saleSettle it: Ask Seattle Public Utilities and Seattle City Light how separate ownership affects metering. | +5 | No score change |
| Trees: 46 percent canopy, a tall tree in the band and a larger one 2.7 ft off the lot line, tiers unknownToss-upIf it goes wrong: a tree that controls where the tight footprint can sitSettle it: Have an arborist measure and tier the trees. | +5 | No score change |
| Street or alley improvements for a new dwelling on an apparently unpaved the frontage streetToss-upIf it goes wrong: a large unpriced street or alley improvement billSettle it: Ask whether street or alley improvements apply. | +5 | No score change |
| Drainage on slow-draining till under the 2026 stormwater code, plus unpriced site workToss-upIf it goes wrong: a detention tank or vault and $15,000 to $60,000 of site work outside the budgetSettle it: Ask Seattle Public Utilities for a water, drainage and wastewater availability certificate. | +3 | No score change |
| Sewer route past the house to a 1958 alley side sewer, or to the street sewerToss-upIf it goes wrong: a new side sewer or lateral repairSettle it: Ask Seattle Public Utilities for a water, drainage and wastewater availability certificate. | +3 | No score change |
| Sewer route: shared side sewer with 8432 the frontage street to a 1958 alley combined sewer, or to the street sewerToss-upIf it goes wrong: The shared or old sewer cannot take a second connection, or needs shared-sewer legal documents or a new run, adding costSettle it: Ask Seattle Public Utilities for a water, drainage and wastewater availability certificate. | +3 | No score change |
| Fire hose pull to a unit 51 to 79 ft in, with an unpaved street and a side-strip pathLikely fineIf it goes wrong: a required sprinkler systemSettle it: Ask about fire access to a unit between the house and the street. | +1 | No score change |
Settle the ones that could end it first: if one goes wrong, the plan may stop there. Each item that clears moves the reading up; how far depends on what the documents show. Checking a task records progress only. A reviewed finding changes the score; only an evidence-based review can change the rating.
| Finding | Status | Source |
|---|---|---|
| King County parcel withheld, in the City of Seattle, in the withheld addition (recorded in the assessor's legal description as unrecorded street and alley values included in adjoining lots). Interior lot, not a corner. Lot area 5,176 sf per the assessor; the mapped outline measures 5,177 sf, about 40 ft wide by 130 ft deep. the frontage street is at the west end and an alley at the east end. | verified (area); inferred (shape and which end is the street, until a survey) | King County Assessor, eReal Property and King County, Parcel Information map, read 2026-11-05 |
| Owner of record withheld. Assessed value for tax year 2027: land $304,000 plus improvements $234,000, $538,000 in all (tax year 2026: $337,000 plus $177,000, $514,000). Sale history was not read. | verified | King County Assessor, eReal Property, read 2026-11-05 |
| Existing house: built 1931 per the assessor, one single-family house of 1,440 sf of living area, 3 bedrooms, 1.75 baths, average condition. The assessor page does not list a basement, garage, porch or number of stories; 1,440 sf of living area against a roof of about 1,230 sf suggests part of the house is a second level or half-level, which a survey and a look at the house settle (if it is one story the footprint is larger and the free ground smaller). On the aerial the roof measures about 40 ft along the lot by 30 ft across, roughly 1,230 sf, at the alley end of the lot and at or very near the side line to the left as you face the lot from the street. | verified (assessor); inferred (size and position from the aerial) | King County Assessor, eReal Property and the aerial, read 2026-11-05; a survey settles the footprint |
| The 1931 build year is not proven: the only side sewer permit on the city's card for this address is dated 1958 (permit [permit withheld]), which shows a sewer job, not when the house was built. | unknown | Seattle Public Utilities, side sewer card [card withheld], saved in this study's Documents, read 2026-11-05; the Seattle Municipal Archives or the city's permit microfilm would settle it |
| Permit [permit withheld], "Allow a detached housing unit maintaining an existing unit (no work) per the land use code. Construct a one-family dwelling per plans," one housing unit added, estimated project cost $223,548, applied October 19, 2026. The city's data lists its status as "Reviews In Process." Who applied, its holds and whether it covers this proposal are not shown. | verified (record); unknown (applicant and status in the city's own portal) | City of Seattle, Building Permits data, read 2026-11-05 |
| Permit [permit withheld], re-roof with sheathing replacement, $9,872, applied October 8, 2018, completed. | verified | City of Seattle, Building Permits data, read 2026-11-05 |
| Code complaint [case withheld], opened July 12, 2017, status completed. No open code case found. | verified | City of Seattle, Code Complaints and Violations data, read 2026-11-05 |
| No other building, demolition, grading or septic record was found for this address. Records from before about 2000 are not in the city's online data, and the county health department's septic records were not searched. | verified (city data); unknown (older and health department records) | City of Seattle, Building Permits data, read 2026-11-05 |
| Easements: the assessor page lists no easement or deed restriction. The city's side sewer card shows a handwritten "storm easement" and "agreement" note, with recording numbers that are hard to read, beside an 18-inch storm pipe that runs from the neighbouring lot to the left toward the alley, close to this lot's left side line. Whether either burdens this lot is not known. | unknown | King County Assessor, eReal Property and Seattle Public Utilities, side sewer card [card withheld], read 2026-11-05; the county recorder holds the documents |
| Sewer: public, no septic. The card shows the house's side sewer running east to an 8-inch sanitary sewer in the alley, and an 8-inch sanitary sewer in the frontage street along the street end. | inferred (old hand-drawn card) | Seattle Public Utilities, side sewer cards [card withheld] and [card withheld], read 2026-11-05 |
| Water: inside Seattle Public Utilities' retail water service area. The assessor lists no water district. | verified | Seattle Public Utilities, Retail Water Service Area map data, read 2026-11-05 |
| Flood: FEMA Zone X, area of minimal flood hazard, outside the mandatory flood zone; map panel 53033C0645G effective August 19, 2020. | verified | FEMA, National Flood Hazard Layer, read 2026-11-05 |
| Access: day-to-day access appears to be the alley at the east end; the frontage street in front of the lot appears unpaved on the aerial. Whether the street is an improved city street and the alley's width and surface are not known. | inferred | The aerial, read 2026-11-05; the city's transportation department and a survey settle it |
| Covenants, plat restrictions or a homeowners association: none found. | unknown | King County Assessor, eReal Property, read 2026-11-05; a title report settles it |
| A small building about 35 ft long sits along the lot's right side line (the south side as you face the lot from the street) and may touch it; it probably belongs to the neighbour. | inferred | The aerial, read 2026-11-05; a survey settles it |
The lot is zoned Neighborhood Residential (NR), the single zone the city created on January 21, 2026 from its three former single-family zones, and this lot was the former 5,000 sf zone. The rules below are read from the city's Ordinance 127376, which rewrote them, and from the city's published guidance as of July 6, 2026; section numbers follow the ordinance and the city's online code may number them differently. Where those two disagree both values are shown. The state requires the city to allow at least two accessory dwellings per lot, a size of at least 1,000 sf, no owner-occupancy requirement, and condominium sale of an accessory unit (RCW 36.70A.681, read 2026-11-05); the city's rules below meet or exceed each of those floors.
| Rule | What it requires here | Code section | Status |
|---|---|---|---|
| Use and count | A backyard home (a detached accessory dwelling unit) is allowed on a lot with a house. The city allows up to two accessory units per lot, attached, detached or stacked, which equals the state's floor of two; the city's two is its own cap. Accessory units count toward the density limit of one home per 1,250 sf of lot (4 homes on this lot). | Seattle Municipal Code 23.42.022.C and J; 23.44.060.A.4, Ordinance 127376, read 2026-11-05 | verified |
| Size | 1,200 sf of gross floor area for a unit with three or more bedrooms (1,000 sf for two or fewer). Up to 250 sf of attached garage, below-ground floors and 35 sf of bike parking do not count. The requested 1,200 sf, 3 bedroom unit is at the cap. | Seattle Municipal Code 23.42.022.G.1 and G.2, Ordinance 127376, read 2026-11-05 | verified |
| Height | 32 ft, plus up to 5 ft for a pitched roof of 4:12 or steeper; 42 ft where the lot keeps a Tier 1 or Tier 2 tree. A backyard home follows the house's height standard. A structure inside a required yard is limited to 12 ft. | Seattle Municipal Code 23.44.070.A and B, Ordinance 127376, read 2026-11-05 | verified |
| Lot coverage | 50 percent of the lot, 2,588 sf here. The city's July 2026 guidance showed 35 percent with one home and 50 percent with a backyard home added; both readings give 50 percent here. | Seattle Municipal Code 23.44.080.A, Ordinance 127376; SDCI, Accessory Dwelling Units code updates, city guidance dated July 6, 2026 | verified |
| Floor area ratio | With two homes on this lot the limit is 0.8 of the lot, 4,141 sf of chargeable floor area (1.0 if further standards in 23.44.050.D are met). The city's July 2026 guidance said accessory units are exempt; the ordinance text read here does not carry that exemption, so the unit is counted. | Seattle Municipal Code 23.44.050.B and C, Ordinance 127376, read 2026-11-05 | verified (ordinance); unknown (which the city applies) |
| Yards | Front 15 ft (the street end). Sides 5 ft on average and 3 ft at the least; the city's guidance says 5 ft, and this study plans to 5 ft. At the alley end a backyard home needs no setback; elsewhere at the rear 5 ft. | Seattle Municipal Code 23.44.090, Table A, note 3, Ordinance 127376, read 2026-11-05 | verified (front, alley); unknown (side, 3 or 5 ft) |
| Distance from the house | At least 5 ft between structures that contain floor area. | Seattle Municipal Code 23.44.100.A, Ordinance 127376, read 2026-11-05 | verified |
| Parking | None required for an accessory unit. | Seattle Municipal Code 23.42.022.I, Ordinance 127376, read 2026-11-05 | verified |
| Owner living on site | Not required; the state bars the city from requiring it. | RCW 36.70A.681(1)(b), read 2026-11-05 | verified |
| Minimum lot for a backyard home | None found in the accessory unit section. | Seattle Municipal Code 23.42.022, Ordinance 127376, read 2026-11-05 | inferred |
Selling the unit as a condominium. The city's code says its land-use rules may not be read to prohibit the sale or other conveyance of a condominium unit on the ground that it was built as an accessory dwelling unit (Seattle Municipal Code 23.42.022.K, Ordinance 127376, read 2026-11-05), and state law says the same (RCW 36.70A.681(1)(k), read 2026-11-05), so the sale itself is allowed. Both statements are verified. The mechanics are not settled in this study. Creating a condominium means recording a declaration and a survey map and plans with the King County Recorder, which publishes a condominium map fee (King County Recorder, Surveys, plats and condos, read 2026-11-05); which chapter of state law governs a condominium created now, whether the city asks for any permit or review to create one, and how the assessor sets up the new unit parcels were not confirmed, and a Washington real estate attorney and the county offices settle them. A unit lot subdivision (a separate lot for the backyard home) is a different route: the city's rule on it was not read, one secondary source says the city's rules bar separating an accessory unit onto its own lot, and a two-lot split of this 5,176 sf lot is not allowed because new lots must be at least 5,000 sf (Seattle Municipal Code 23.44.060.B, Ordinance 127376, read 2026-11-05). Water and power metering for separately owned units is covered under Utilities. Status: allowed in principle (verified); process unknown.
The existing house and the older-than-the-rules question. The 1931 house predates the current yard rules and appears to sit at or against its left side line, closer than the 5 ft side yard the code now asks for, so it is probably a legally nonconforming structure; whether it is, and what the city's nonconformity section (Seattle Municipal Code 23.42.112, text not read in this study) limits on expansion or rebuilding after damage, is unknown until a survey measures the house and the city confirms the section. This study does not rely on it: a backyard home is a separate building, nothing is proposed for the house, and the lot-wide coverage and floor-area limits count both buildings together (inferred). Any later enlargement of the house would depend on that section and on the city's own damage and improvement threshold, which may be computed on replacement cost rather than assessed value. The federal 50 percent flood test does not apply: the lot is in Zone X outside the mandatory flood zone. Status: house conformance unknown; flood test not triggered (verified).
| Hazard | On this lot? | What it triggers |
|---|---|---|
| Landslide-prone area (the city's "potential slide area") | Yes. The city's map covers 1,999 sf, 38.6 percent of the lot, as a band across the full width beginning at the street-end lot line and reaching 47.8 ft deep on the left side of the lot to 51.2 ft on the right. The lot itself is nearly flat (1.7 ft of relief, 4 percent at most), so this is a mapped regional hazard, not a slope on the lot. verified | The city's environmentally critical areas code, Seattle Municipal Code 25.09, generally asks for a geotechnical report by a licensed engineer for building in such an area. The code text for exemptions and relief was not confirmed in this study; a small-project waiver and a determination that a unit placed outside the mapped area is not touched by the rules are both possible and unconfirmed. See What it takes, steps 5 and 11. |
| Steep slope (city map) | No. The nearest mapped steep slope is 76.6 ft from the lot across the street end. Whether its buffer reaches the lot is unknown, but a buffer would have to exceed 76.6 ft to do so. verified (distance); unknown (buffer) | Development in a steep slope or its buffer is restricted; the surveyor and geotechnical engineer plot any buffer. |
| Known slide, liquefaction, peat settlement, wetland, riparian corridor, flood-prone area, historic landfill, shoreline | No, and none within 600 ft except a wetland 511 ft away and a shoreline 510 ft away. verified | Nothing. |
| Fish and wildlife habitat (a state-mapped biodiversity area, the East Duwamish Greenbelt) | Not on the lot; the mapped edge is 5.2 ft beyond the street-end line at the far front corner. Whether it is a regulated habitat area with a buffer that reaches the lot is unknown. unknown | A buffer or habitat review is possible; the city's critical-areas staff confirm. |
| Flood | No. FEMA Zone X; the city's flood-prone map shows nothing on the lot. verified | No flood permit and no elevation certificate. |
| Trees | About 46 percent of the lot lies under mapped tree crowns. The city's laser survey puts a tall tree (about 68 ft) inside the landslide band and another (about 82 ft) 2.7 ft beyond the lot line. Their trunk diameters and tiers are not known. inferred | The city's tree protection rules (Seattle Municipal Code 25.11) sort trees into tiers by trunk diameter; a Tier 1 or 2 tree generally may not be removed except where needed to reach the building capacity the code allows, and keeping one lifts the height limit to 42 ft. Rules for replacement are described differently in different city documents, so treat them as unconfirmed. |
| Environmental review (SEPA) | State rules exempt building up to four single-family homes (WAC 197-11-800(1)(b)), and a house plus one backyard home is two. Whether the city's rules for critical areas pull a project here back into review is unknown. unknown | A checklist and a threshold decision are possible. See What it takes, step 6. |
The surface geology under the lot is mapped as Lawton Clay (silt and clay) and the soil survey calls the soil Urban land and Alderwood, a till soil that drains slowly, so drainage design needs care (inferred). The city's permit data for the open application does not say whether the lot is in a critical area, so its status needs confirming (What it takes, step 1). The city began a rewrite of its critical-areas code on September 29, 2026; no draft or adoption date exists yet.
Water is Seattle Public Utilities (SPU). The state Department of Health lists SPU's water system operating permit as Green, valid through May 31, 2027, as of November 5, 2026; Green means the system is adequate for growth up to its approved number of connections, and the approved count was not published, so it was not checked (Washington State Department of Health, system 77050, read 2026-11-05). The house is on the city sewer, through a side sewer to the alley; the old city card also shows a sanitary sewer in the frontage street, which may give the unit a second possible connection point, depending on its depth and whether the street is improved. Sewage is treated by King County, which bills its own capacity charge. Power is Seattle City Light. Which of the mapped lines near the lot are sanitary and which combined with storm, the size and condition of the 1958 side sewer, and where the water main that serves the lot lies are not known; SPU's availability certificate answers them.
Separate ownership raises two metering questions. SPU's rule for water service says each legal parcel gets one domestic water service and that SPU will not approve extra services to bill separate building owners; the rule does not mention condominiums, so whether a condominium unit may have its own meter is unknown (Seattle Public Utilities, Director's Rule WTR-440, read 2026-11-05). Seattle City Light's 2026 service requirements require a meter for each legal dwelling unit except accessory units, and the rule does not say whether a condominium-owned backyard home still counts as an accessory unit (Seattle City Light, Requirements for Electric Service Connection, 2026 edition, read 2026-11-05). Both utilities answer; see What it takes, step 3. Whether a 2026 water-and-drainage rule keeps new roof and paving water out of formerly combined sewers in this basin is unknown (SPU answers).
Directions come from the lot's measured orientation: the frontage street is at the west end, the alley at the east end, and the left side as you face the lot from the street is the north side.
| Measure | Result |
|---|---|
| Lot | 5,176 sf, about 40 ft wide by 130 ft deep |
| Setbacks used | Front 15 ft, sides 5 ft, alley end 0 ft, 5 ft from the house |
| Landslide band | Street end of the lot, 47.8 to 51.2 ft deep (taken as 52 ft here); 1,999 sf |
| House footprint | About 1,230 sf, at the alley end, measured from the aerial (an estimate) |
| Free area for a detached unit, whole lot | 1,890 sf; the largest clear rectangle is 30 ft by 63 ft, west of the house |
| Free area for a detached unit, outside the landslide band | 780 sf; the largest clear rectangle is 30 ft by 26 ft, west of the house |
| Unit sizes tested | A 1,200 sf unit as two stories on a 600 sf footprint (24 ft by 25 ft, or 20 ft by 30 ft) fits outside the band. A 1,200 sf unit in one story (30 ft by 40 ft) fits only by reaching into the band. Two such 600 sf footprints together, kept 5 ft apart, fit only on the whole lot; outside the band the planner found room for one. |
| Lot coverage with the unit | House 1,230 sf plus unit 600 sf is 1,830 sf, about 35 percent. The limit is 50 percent. |
| Floor area with the unit | 1,440 sf of house plus 1,200 sf of unit is 2,640 sf, under the 4,141 sf limit for two homes. |
Areas from the county parcel map, the setbacks above and an aerial measurement of the house; a survey can move every area.
| Path | Can it be done? | What decides it |
|---|---|---|
| Backyard home, 1,200 sf (3 bed, 2 bath), sold as a condominium unit | Conditional | Fits as a two-story outside the mapped landslide band. Needs the city's answer on the landslide area, the status of the open application, and how separate ownership meets the water and power metering rules. |
The open ground is the strip between the street end and the house, because the house sits at the alley end, and the landslide band takes the street end of that strip, so a 1,200 sf unit fits outside the band only by stacking it on a 600 sf footprint. Lot coverage is not the limit and no parking is required, so no further workaround is needed; the unit sits about 53 to 79 ft in from the street-end lot line, with its east wall 5 ft from the house. A unit reached from the alley passes the house's right side (the south side), where the strip between the house and the side line is the only way for utilities and walkway to run.
| Finding | Status |
|---|---|
| An application for a detached housing unit ([permit withheld]) is open on this lot; who filed it and whether it covers this proposal are not known. | verified (record); unknown (applicant) |
| The city's landslide-prone area covers the street-end 48 to 51 ft of the lot. A unit outside it may still need a determination, and a unit reaching into it needs a geotechnical report and may be limited by it. | verified (mapping); unknown (how the rules apply) |
| Whether environmental review (SEPA) applies because the lot touches a critical area. | unknown |
| Whether SPU and Seattle City Light will meter a condominium-owned backyard home separately, or require it to share the house's services. | unknown |
| Whether the alley sewer, the old street sewer and the water service can take a second connection, and how roof and paving water must be handled under the 2026 stormwater code. | unknown |
| A possible recorded storm easement and agreement beside the lot's left side line. | unknown |
| Street or alley improvements may be required for a new dwelling, and the frontage street appears unimproved. | unknown |
| Fire access: the unit sits 53 to 79 ft in from the frontage street (about 51 to 77 ft from the alley, behind the house), and the street frontage appears unpaved, so hose-pull distance from the street or from the alley along the right side strip, and the nearest hydrant, are unconfirmed. | unknown |
| The survey will settle the true lot lines, the house's footprint and left-side-line distance, the building along the right side line and the 1931 build year. | inferred |
| Trees: a large tree in the band, a larger one beside the lot line and 46 percent canopy cover. | inferred |
| The condominium itself: the declaration, the survey map, the lender's consent if there is a mortgage, and the legal chapter that governs. | unknown |
| A 3 bed, 2 bath layout in 1,200 sf must meet the residential code's bedroom, egress and stair rules, which were not read. | unknown |
| Study | Why this parcel needs it | Who prepares it | What it settles |
|---|---|---|---|
| Geotechnical report | A mapped landslide-prone area covers the street end of the lot. | A Washington-licensed geotechnical engineer or geologist | Whether and where the unit can be built, and foundation conditions. |
| Boundary and topographic survey | Setbacks, a building along the right side line, the band's edge and tree locations all depend on exact measurements, and the condominium map builds on it. | A Washington-licensed land surveyor | Lot lines, true setbacks, existing paving, the band's edge. |
| Arborist report and tree protection plan | About 46 percent of the lot is under tree crowns. | A certified arborist | Tree tiers, removal and replacement, whether the 42-ft height limit is available. |
| Drainage plan | The city's 2026 stormwater code applies to applications completed on or after July 1, 2026, and the soil drains slowly. | A civil engineer or the project's designer | How roof and paving water is handled and whether the drainage charge applies. |
| Condominium declaration and survey map | The unit is to be sold separately. | A real estate attorney and a land surveyor | Ownership, shared services and maintenance terms, and a recordable map. |
| SEPA checklist | Required only if the city finds the exemption does not apply at the critical area. | The applicant's designer, reviewed by the city's planning office | Whether environmental review adds time and fees. |
About $709,000 for the 1,200 sf backyard home, within a range of about $453,000 to $938,000.
| Item | Low | Likely | High |
|---|---|---|---|
| Construction1,200 sf at $350 / $537.50 / $700 per sf | $420,000 | $645,000 | $840,000 |
| City building permit and plan reviewpermit and plan review, worked out at $213,156 (low) and the construction band (high), with fees | $5,687 | $10,448 | $15,208 |
| City review feesdrainage review and pre-application, up to critical-area and environmental review | $767 | $3,813 | $6,859 |
| Seattle Public Utilities side sewer and drainageside sewer permit and drainage charge on 600 to 1,200 sf of new hard surface | $1,015 | $1,618 | $2,220 |
| Seattle Public Utilities water charges$0 on the house's service; $14,300 for a new 3/4-inch meter and service | $0 | $7,150 | $14,300 |
| County sewer capacity charge0.59 unit at $77.99 a month for 15 years | $8,283 | $8,283 | $8,283 |
| Seattle City Light serviceoverhead or underground 200 amp service, standard charge | $1,436 | $3,354 | $5,273 |
| Utility connection workwater, sewer and power runs to the unit | $10,000 | $18,750 | $30,000 |
| Condominium map and declaration recordingKing County recording fees, 10 to 40 page declaration | $736 | $752 | $766 |
| Geotechnical report | $3,000 | $5,750 | $10,000 |
| Boundary and topographic survey | $1,500 | $2,750 | $4,000 |
| Arborist report | $450 | $975 | $1,500 |
| Total | $452,874 | $708,643 | $938,409 |
What this budget covers
Included:
Not included:
No floor plan was matched; construction is priced from published market costs per square foot.
Site work beyond a flat building pad (drainage, tree work, a walkway and utility trench past the house) is not in the totals; published ranges put it at $15,000 to $60,000 for difficult sites.
The fee lines above are built from the schedule in Fees the city publishes, below.
| Fee | Amount |
|---|---|
| Building permit | 100 percent of the city's development fee index at the construction value (Seattle Municipal Code 22.900D.010, Tables D-1 and D-2). Above $250,000 the index is $2,984 plus $7.50 per $1,000 up to $500,000, $4,859 plus $7 per $1,000 from $500,000, and $6,609 plus $7 per $1,000 from $750,000. SDCI sets the value. Below $250,000 the index is $2,402.75 plus $7.75 per $1,000 above $175,000. Worked out at the published building-valuation minimum for 1,200 sf ($213,156), the index is $2,705; at the construction band's high end, $840,000, it is $7,239. |
| Plan review | 100 percent of the same index. Half the permit fee plus the plan review fee is due at application; the rest at issuance. |
| Technology fee and state fee | 5 percent of the city's fees (22.900A.100), and $6.50 on each residential permit (RCW 19.27.085). |
| Building permit total, worked out | Permit plus plan review plus the technology fee plus $6.50: $5,687 at the $213,156 value and $15,208 at $840,000; the budget line runs between them, with $10,448 as its midpoint. |
| Drainage review | Minimum one hour at $292, $292 (Table D-SR). |
| Critical-area review and exemption review | Minimum half an hour at $292 each, $146 each (Table D-SR), only if the city requires them. |
| Building pre-application conference | 1.5 times the $292 base fee, $438 (22.900D.010.I.2). |
| Land-use review, if environmental review applies | $551 an hour, with a 10-hour minimum of $5,510 for the general land-use category (Table C-1). |
| Pre-application site inspection | Three-quarters of an hour, $219 (Table D-SR). |
| Tree review on a permit | $551 (Table C-1, row 40). |
| Review fees line, worked out | Low: drainage review plus the conference, $730. High: those plus critical-area review, exemption review and the 10-hour land-use minimum, $6,532. Each with the 5 percent technology fee: $767 to $6,859. |
| Third-party geotechnical review, if the city hires one | The city's contract cost plus its hourly time (22.900D.145.E). |
| Electrical permit | By the value of the work (Table D-14 with plan review); a new service of up to 125 amps is $146 and of 150 to 200 amps $292 without plan review (Table D-15). The value is unknown until design. |
| Plumbing and gas piping permits | Issued by Public Health, Seattle and King County, not the city; the amount was not found. |
| Side sewer permit | $375 for the first connection, $280 for each additional connection, $375 for a storm drain connection (Seattle Public Utilities, Director's Rule FIN-220.2, section 3.H). The line uses $280 to $750. |
| Water and wastewater system development charges | $6,900 and $2,600 for a new 3/4-inch meter; none where the unit shares an existing service (Seattle Public Utilities, Director's Rule FIN-219 section D, and FIN-220.2 section 3.B). Installing a new 3/4-inch service adds $4,800 (non-arterial street) or $6,175 (arterial), section 3.A. Whether the frontage street is an arterial is unknown, so the line uses the non-arterial rate: it runs from $0 (shared service) to $14,300 (new meter: $6,900 plus $2,600 plus $4,800). |
| Drainage system development charge | $1,225 for each 1,000 sf of new hard surface (FIN-220.2 section 3.B.2): $735 for a 600 sf roof footprint and $1,470 for 1,200 sf, worked out. The side sewer and drainage line uses $1,015 to $2,220. |
| County sewer capacity charge | 0.59 of a residential unit for a detached accessory unit at $77.99 a unit a month, $46.01 a month for 15 years, worked out as $8,283 in all (the rate and the weight are published; the total is worked out); the county's 2027 rate is not confirmed (King County Wastewater Treatment Division, capacity charge). A discounted lump sum is available. |
| Seattle City Light service | Standard charge for a 200-amp single-phase service: $1,436 overhead or $5,273 underground (Seattle City Light, Service Installations policy, effective June 25, 2025); line extensions are billed at cost. A newer schedule may be higher; confirm with the utility. |
| Condominium recording | Condominium map at 18 by 24 inches $423.50 plus $0.50 for each additional lot; other documents $303.50 plus $1 per additional page (King County Recorder, Surveys, plats and condos, effective 2024-01-01, and Document recording). For a 10 to 40 page declaration the two total $736 to $766, worked out. |
| Unit lot subdivision, if used instead of a condominium | $5,510 land-use minimum plus $73 building review, each with the technology fee, plus recording. Whether it is allowed for a backyard home is unknown. |
| Impact fees | None found. Seattle is reported not to charge transportation, park, school or fire impact fees; confirm with the city's planning office. |
The building and review fees are from the city's 2026 fee schedule, effective January 1, 2026; a replacement 2027 schedule had not been adopted as of November 5, 2026. The utility charges are from Seattle Public Utilities' Director's Rules FIN-219 and FIN-220.2, effective January 1, 2026. The county rate applies to connections on or after January 1, 2026, and the county bills the capacity charge about three months after the connection. Since May 4, 2026 the drainage charge is invoiced with the side sewer permit and is due before that permit issues.
| Date | Finding | Source document | Status |
|---|---|---|---|
| January 21, 2026 | The Neighborhood Residential zone took effect; lot coverage is 50 percent and a backyard home may be up to 1,000 or 1,200 sf. | Seattle Ordinance 127376 | verified |
| January 21, 2026 | Revised tree protection rules took effect for the zone (Ordinance 127300). | Seattle Department of Construction and Inspections, tree protection regulations | verified |
| July 1, 2026 | The city's 2026 stormwater code and manual (Ordinance 127444) apply to applications completed on or after this date. The thresholds for a backyard home were not confirmed. | City of Seattle Legislative Information, Council Bill 121190 | verified (adoption); unknown (thresholds) |
| September 29, 2026 | The city announced an update of its critical-areas code; an open house is tentatively January 2027. No draft or effective date; it could change the geotechnical and relief rules for this lot. | Seattle Department of Construction and Inspections, Environmentally Critical Areas update | verified |
| November 5, 2026 and November 20, 2026 (expected) | Council hearing and expected adoption of the 2027 to 2028 budget, which proposes about 10.7 percent higher building and land-use fees; a fee bill (Council Bill 121310) is in committee. Not enacted. | Seattle Department of Construction and Inspections, proposed 2027-2028 budget | inferred |
| November 5, 2026 | The Department of Health lists Seattle Public Utilities' water system operating permit as Green, valid through May 31, 2027. | Washington State Department of Health, system 77050 | verified |
| Through November 5, 2026 | No moratorium or pending change to accessory-unit, zone, height, coverage or condominium rules was found in the Council's legislation titles since July 6, 2026, searching titles only; no water or sewer connection restriction was found. | Seattle City Council, Legislative Information Service, search window July 6 to November 5, 2026 | inferred |
| Not dated | A draft resolution on an inclusionary requirement for the neighbourhood residential zone was heard in committee on July 2, 2026; it is a draft, not law. | Seattle City Council, Legislative Information Service | inferred |
Parcel documents found
RentCast property records · Retrieved 2026-11-05
| Latest annual property taxes | $4,778.00 |
|---|---|
| Tax year | 2024 |
| Assessment year | 2024 |
| Land assessed value | $337,000.00 |
| Improvement assessed value | $141,000.00 |
| Total assessed value | $478,000.00 |
| Parcel ID | withheld |
| Tax year | Annual taxes |
|---|---|
| 2024 | $4,778.00 |
| 2022 | $4,642.00 |
| Sale date | Sale price |
|---|---|
| 2026-06-18 | $485,000.00 |
| 1995-04-28 | $104,950.00 |
Official county assessor records (search by the address or parcel ID)
Historical tax record; too old to prefill a current tax assumption.
Assessed value is a tax assessment, not a market valuation or land acquisition cost. Existing-property taxes may change after construction or reassessment.
Start with the city's planning and permit office, SDCI, because the open application on this lot and the landslide and environmental-review questions are answered there. A building and land-use pre-application is named as the first step in the city's backyard-cottage guidance (Tip 116B, as described on the city's ADU page); the guide itself could not be read here and no code section requiring a conference for a single backyard home was found, and the fee schedule prices a building pre-application conference you request at $438 (Seattle Municipal Code 22.900D.010.I.2). Request one through the Seattle Services Portal.
| Office | What to contact them about | How to reach them | Status |
|---|---|---|---|
| Seattle Department of Construction and Inspections (SDCI), planning, land use, trees and building permits | Step 1, the open application [permit withheld]; step 5, the pre-application conference and the landslide-area question; step 6, environmental review; step 7, street and alley improvements; step 8, fire access; step 10, tree tiers; step 15, the building permit handed in through the portal | (206) 684-8600 · SCI_ASC_Support@seattle.gov · https://www.seattle.gov/sdci/permits/common-projects/accessory-dwelling-units (portal https://cosaccela.seattle.gov/Portal/) | verified July 6, 2026 |
| Seattle Public Utilities (water, side sewer, drainage) | Step 2, the availability certificates; step 3, water metering for separate ownership; step 13, the drainage answer; the side sewer permit and drainage charge | (206) 684-3333 (development services office) · SPU_DSO@seattle.gov · https://www.seattle.gov/utilities/construction-resources/water/water-availability-certificate | verified July 6, 2026 |
| Seattle City Light | Step 3, power metering for separate ownership; step 15, a second service | (206) 233-2777 · https://sclesr.seattle.gov/sclesrintake/ | verified August 24, 2026 |
| Seattle Department of Transportation (street and alley right-of-way) | Step 7, whether the frontage street and the alley must be improved, and the alley's width | Start at https://www.seattle.gov/transportation | unknown |
| Seattle Fire Department (fire plan review) | Step 8, hose-pull distance, hydrant location and a path to the unit | Start at https://www.seattle.gov/fire | unknown |
| King County Recorder's Office | Step 4, copies of the recorded storm easement and agreement; step 12, recording the condominium declaration and map | 206-477-6620 · KCROCust@kingcounty.gov · https://kingcounty.gov/en/dept/executive-services/certificates-permits-licenses/records-licensing/recorders-office/surveys-plats-condos | verified |
| King County Department of Assessments | Step 12, how the new condominium unit parcels are set up; also any lot-size question the survey raises | 206-296-7300 · Assessor.info@kingcounty.gov · https://kingcounty.gov/en/dept/assessor | verified |
| King County Wastewater Treatment Division | The sewer capacity charge and which category a condominium-owned backyard home falls in; no step needed before the connection | 206-296-1450 · CapChargeEscrow@kingcounty.gov · https://kingcounty.gov/en/dept/dnrp/waste-services/wastewater-treatment/sewer-system-services/capacity-charge/about | verified |
| Public Health, Seattle and King County, on-site sewage and drinking-water program | Not needed. The house is on the city's sewer and water, so no septic system or well is in play; it would become needed only if one were proposed. | 206-477-8050 · https://kingcounty.gov/en/dept/dph/health-safety/environmental-health/on-site-sewage-systems | verified |
| Washington 811, the state's one-call locate service | Before the test borings in step 11 and any trenching | 811 · https://www.wa811.com | verified |
| Washington Board of Registration for Professional Engineers and Land Surveyors | Checking the licence of the geotechnical engineer, land surveyor and structural engineer in steps 9, 11, 12 and 14 | 360-664-1575 · https://brpels.wa.gov/about-us/contact-us · https://professions.dol.wa.gov/s/license-lookup | verified |
| Washington Geologist Licensing Board | Checking a geologist's licence if the geotechnical report in step 11 is by a geologist | 360-664-1497 · geologist@dol.wa.gov · https://dol.wa.gov/professional-licenses/geologists/frequently-asked-questions-geologists | verified |
| Washington State Board for Architects | Checking the licence of the architect in step 14 | dolboards@dol.wa.gov · https://dol.wa.gov/professional-licenses/architects/washington-state-board-architects | verified |